LAFAYETTE BUILDING

Client: Megaworld Corporation

Mandurriao Iloilo City

March 2016 – June 2018

1.4MW LOWER LABAYAT MINI HYDRO POWER PROJECT AND 1.3MW UPPER TIGNAOAN MINI HYDRO POWER PROJECT

Client: BLUE ENERGY HOLDINGS & MANAGEMENT GROUP

San Juan City

Project Location: Real Quezon

Date: June 2017 – March 2020

CENTRAL PHILIPPINE UNIVERSITY

Client: CENTRAL PHILIPPINE UNIVERSITY

Jaro, Iloilo

July 2017 – May 2018

THE ROCHESTER TOWER C (BRIDGEVIEW)

Client: EMPIRE EAST LAND HOLDINGS, INC.

San Joaquin Pasig, City

Date: November 2017 – March 2020

CONCRETING OF BRGY. PAMPANGO-ROSAL-LUGTUCA-MANIKA FMR WITH 4 BRIDGES

Client: PROVINCE OF AKLAN

Province of Aklan

Date: March 2017 – June 2018

YOLANDA HOUSING PROJECTS (5 SITES)

Client: NATIONAL HOUSING AUTHORITY

Cebu, City

Date: January 2018 – January 2019

CONSTRUCTION OF 3-STOREY 15 CLASSROOMS BLDGS (5 SITES)

Client: NATIONAL HOUSING AUTHORITY

Cavite, City

Date: January 2018 – January 2019

CONSTRUCTION OF TWO (2) DIVERSION DAMS OF AKLAN RIS (EAST SIDE & WEST SIDE)

Client: NATIONAL IRRIGATION AUTHORITY

EDSA, Diliman Quezon City

Date: January 2018 – January 2020

CONSTRUCTION OF SAGAY FEEDER PORT/FISH LANDING

Client: PROVINCE OF NEGROS OCCIDENTAL

PROVINCE OF NEGROS OCCIDENTAL

Date: January 2018 – April 2019

ILOILO BOUTIQUE HOTEL AND DISTRICT (PHASE II)

Client: MEGAWORLD CORPORATION

Mandurriao, Iloilo City

Date: September 2016 – March 2018